Case Study
Case Study
Chiller Retrofit for
PP Film Factory
West Java | Bekasi
Chiller Retrofit For
PP Film Factory
West Java | Bekasi
Chiller Plant Audit
TEDES conducted a field survey to audit the existing Chiller Plant and indentify problems..
Analyze & Calculate
TEDES conducted an analysis to find solutions related to the Chiller Plant problems found during the survey and performed design calculations according to the Chiller Plant requirements.
HVAC Design & Equipment Selection
TEDES design New Centrallized Chiller Plant to replace existing chiller units and selected the most suitable chiller system for the customer and the new proposed system could save more than 50% energy usage compare to the old system.
Implementation
Customer purchased the first chiller and proved that the projected 50% saving could be achieved.
Monitoring
TEDES monitor the chiller performance while discussing implementation of the completion of the new chiller plant.